Construction Update: Fall 2017


Adam MacIver of Verity Construction and his team of contractors have had a very productive Summer!

The plan is to complete the finishings inside the building starting from the top down. The drywallers have made it down to the fourth level, paint will come next week and cabinets the following. The third level is ready for insulation and rough-ins. The exterior cladding is getting applied to the western and southern elevations.

Your Options and Upgrades Coordinators, Sheri Martin and Mallory Robertson, have met with every Lakepoint One Condo Owner and can’t wait to see everything come together.